The main idea, which came out trough different presentations at Eesti Energia Environment Day was that, although a number of oil shale industries by-products are in terms of legislation defined as waste, they can often be seen rather as products or as raw materials, which can be used to the maximum extent, only if there are good ways how to use them.
More detailed information about Eesti Energia Environment Day is available at the companies’ blog in Estonian here:
Short film about mass-stabilisation principles and works at Simuna-Vaiatu pilot site can be found from projects webpage under news section.
]]>After the presentation, all participants had an opportunity to visit a Simuna Vaiatu test section, and ask questions from the project parties about the technology and the use of materials.
]]>After the construction works sections are monitored for few years to in order to obtain information about the various sections of ash mixes stabilized behavior. According the current plan road sections monitoring at least until year 2016.
]]>Images of the object construction can be viewed in the gallery.
Technical reports can be accessed through a link on the documents.
]]>On 20 July 2012, the Estonian Road Administration issued road construction permit No. 11 to Estonian Energy for state road No. 12109 Narva-Mustajõe section km 14.0-16.1. The completion date is set out for 31. December 2012.
Operations Construction works are carried out by Nordecon AS in accordance with road construction project compiled by Ramboll Estonia AS.
On this road section will be built two sections with different construction will be built:
1. Test-section where the oil shale ash is used to stabilize an existing foundation (different ash-stabilized layer thicknesses and different ashes);
2. Test-section using traditional methods where complex-stabilized foundation will be built.
On 1 August 2012, the Estonian Road Administration issued road construction permit No. 14 to Estonian Energy for state road No. 17192 Simuna-Vaiatu section km 3.0-4.0. The completion date is set out for 31. December 2013.
Construction works Operations are carried out in several phases by Nordecon AS in accordance with road construction project compiled by Ramboll Estonia AS.
On this road section will be built the following constructions test-sections with the following constructions will be built:
1. Test-section where the oil shale ash is used to stabilize an existing foundation;
2. Test-section where sub-soil (peat) mass-stabilization will be carried out;
3. Test-section using traditional methods where a complex-stabilized or crushed stone foundation will be built.
On Simuna-Vaiatu section mass-stabilization works will use a binder mixture where one component is oil shale ash from Estonian Energy power plant filter block 8 or cyclone ash, and other component is composite cement.
Laboratory tests were conducted in the Ramboll Finland Luopioinen laboratory, in order to develop the most appropriate recipe for tested materials.
]]>The conference program and further information can be found http://www.ngm2012.dk.
]]>More information about the conference agenda and the content can be found www.swedgeo.se/wascon2012.